Q. Do
I have to buy supplies, equipment, etc. that are on an agency/state
contract especially if I can buy it cheaper somewhere else?
|
A. Yes,
if it is a mandatory type contract.
Agency/state contracts are awarded using the competitive bid
process.
|
|
Q.
What are the dollar limits for Professional and Consulting
Services Contracts?
|
A. Up
to $5,000 can be accomplished on a purchase order.
$5,000.01 to $25,000 must be submitted to OSP for approval.
Over $25,000 will be submitted to OSP and the Legislative
Council for review and advice.
|
|
Q. What
are the types of bid structures and their dollar limits?
|
A. There
are three (3) basic procurement structures related to dollar limit
for most commodities and services.
Note: This
basic structure does not apply to all commodities and services.
Small order:
$.01 - $5,000
Competitive Bid:
$5,000.01 – $25, 000
Competitive Sealed Bid: above $25,000
|
|
Q. Why
can’t I “split” a purchase request when the need is for two
different jobs or paid from two different accounts?
|
A. It
is a violation of Arkansas law to split purchases to circumvent the
bid process.
|
|
Q. Why
must I attach the registration
form to my Purchase Request?
|
A. The
information contained on the registration form in most case, allow
us to process your Purchase Request in an expedient manner.
The registration form will reveal if any other type of
approval is required before the PR can be processed.
For example: items such as meals and lodging require “Direct
Billing” approval from the Department of Finance and
Administration before we can legally process the PR.
|
|
Q. If
I have a grant why do I have to process a Purchase Request?
|
A. Funds
for grants can come from many different sources such as
state(includes UCA, ADHE, DHS and various other state agencies),
federal and private. These
funds are generally taken into the University coffer so the rules
and regulations of the State of Arkansas and the University apply.
We have found that when the UCA method of procurement is
utilized we are legal 99.9% of the time with any grant requirement.
|
|
Q. Why
can’t printing be procured without a bid?
|
A. Amendment
54 of the Arkansas Constitution requires that all Printing and
Stationery be procured using the competitive bid process.
Other Arkansas statutes required the use of recycled paper,
soy ink, etc. for the printing process, thus the only way to satisfy
the full requirement of the law is to bid all printing regardless of
the amount needed.
|
|
Q. Can
I be reimbursed with Petty Cash for the purchase of food items?
|
A. Yes,
if prior written approval has been received from your Vice President
and the purchase will not exceed $50.00.
Submit receipt and written approval to the Purchasing
Department for petty cash reimbursement.
|
|
Q. Is
this item on State Contract?
|
A. Call
Purchasing at 450-3173 or check link under State Contract on the
Purchasing Web Site.
|
|
Q. Can
I pay for meals and lodging on a purchase order for “state
employees”?
|
A. Yes,
if written approval for Direct Billing has been received from the
Department of Finance and Administration.
Allow 7 to 10 working days for the approval process.
|
|
Q. I
have an invoice; what do I do with it?
|
A. Make
sure the purchase order number is on the invoice and send it to
Accounts Payable.
|
|
Q. How
much can I buy before I have to get written quotes or how much
before we have to advertise for bids?
|
A. For
most items, $5,000.01 to $19,999.99 requires (3) three written
quotes for non-labor related items; (4) four written quotes for
labor related items. $20,000
and over must be advertised and bid.
State law requires this.
This does not apply to printing and stationery.
|